Project By EQ-House Personnel

Project:  Alstom HV Substation Rectification Wheatstone Onslow

Application: Plan scope, source suppliers and craft to do work. Prepare and manage all Quality and safety documentation.

Scope: 

The client engaged EQ-House to assist with Site required modifications to the 132Kv substation.   Site visit were conducted to ensure that the full scope was determined prior to mobilisation of craft labour.

The ability to pre-plan enable EQ-House to manage carpentry, electrical, metal fabrication and painting resources on-site to delivery all works two weeks earlier than scheduled.

Quality and safety documentation was paramount to the success of the project with EQ-House engaged continually with end client QC and HSE to ensure compliance to Site requirements